In a Mock Exam from Kaplan the following information is stated:
" GigaTech has estimated real capital costs for the two projects at 10.58%. GigaTech expects inflation to be approximately 4.0% for the foreseeable future."
It seemed as you would just add the real capital costs with the approx. inflation to get 14.58%.
However, Kaplan multiplies the two in the solution as 15.0% = (1 + 0.1058)(1 + 0.04).
Why not just add them?